An institutional owner with more than $100B under management needed to modernize aging air-conditioning across three multifamily communities. The local municipality was pressing for it. The scope was 300 HVAC replacements. The risk was everything around them.
The problem behind the problem
- The electrical infrastructure was aged, and nobody knew whether it had capacity for new high-efficiency units.
- The initial estimate carried $510,000 for building and transformer electrical upgrades on the assumption that it did not.
- The local utility ran its own engineering and build-out pipelines, which threatened to gate the entire schedule.
Run the numbers before you buy the upgrade
We ran a full electrical load calculation on every property. We were the only contractor that did. The calculations confirmed that the new units could be supported by the existing electrical service, which meant most of the assumed building and transformer scope was not needed.
We then took apartment-by-apartment power-source detail to the utility and negotiated transformer and service scope directly, and we sequenced our trades around the utility’s pipelines so that their timeline never gated ours.
| Line | Estimated | Actual |
|---|---|---|
| HVAC systems & duct cleaning | $1,910,000 | $1,910,000 |
| Electrical: unit upgrades | $350,000 | $350,000 |
| Community #1 re-roofing | $250,000 | $250,000 |
| Electrical: building & transformer upgrades | $510,000 | $140,000 |
| Total project cost | $3,020,000 | $2,650,000 |
Where the savings went
The owner kept $370,000, or 12% of the estimated project cost. In practice that money funded scope the owner had not planned for: the program now includes 16 re-roofs alongside the mechanical work.
“They understood the scope and what actually needed to get done, not just what was specified. That saved us enough on HVAC to fund a re-roof and electrical upgrades we hadn’t planned for.”
The lesson for other owners
- 01Do not price an electrical upgrade on an assumption. A load calculation costs little and can remove six figures of scope.
- 02Engage the utility early with unit-level detail. Vague requests go to the back of an engineering queue.
- 03Sequence trades around the longest external lead time, so that no one else’s schedule becomes yours.
- 04Hold mechanical, electrical and roofing under one contract. Savings in one scope can then fund another without a new procurement.
Written by the Air Force Mechanical team from field assessments and active programs.
General guidance only. Confirm code and regulatory requirements for your property.